This page includes a linked Project Map with the locations of recent development and site plan projects in the City of De Pere that are either being revised by the developer (D), under staff review (R), recently approved (A), recently completed (green X), or recently denied (red X). For additional information about a specific project, access to developer contact information, and site plans, click on the project in the List of Projects.
Project Map
List of Projects
Developer Revising Plans:
- 665 Grant ST - West De Pere High School Autos Addition
- 2121 American BL - New Robinson Parking Lot
- 2121 American BL - New Robinson Metal Southeast Warehouse Access Drive
Projects that are Under Staff Review:
Projects that are Recently Approved:
- 925 S Sixth ST - MSC Expansion
- 1100 BLK Employers BL - New Phoenix of De Pere Multi-Unit Residential
- 3001 Ryan RD - Altmayer Elementary School Re-Pavement (includes new pavement)
- 411 Destiny DR - Mobius Parking Restripe and New Playground
- 2000 BLK Profit PL - New Soft Light Photography
- 224 N Wisconsin ST - New De Pere Parking Facility
- 2221 Innovation DR - American 3-Fab
- 2121 American BL - New Robinson West Laydown Yard
- 403-409 N Broadway ST - White Pillars Expansion
- 114 S Ninth ST - New Ninth ST Multi-Tenant Development
- 2005 Commerce DR - New City Composting Yard Waste Site
- 633 Heritage RD - Belmark Plant 3 Expansion
- 2385 Lawrence DR - New Draco Pavement and Screening
- 550 William ST - New 550 West Mixed Use
- 215 N Wisconsin ST - New Towneplace Suites Hotel
- 450 Fortune AV - New Robinson Metal Transportation Terminal & Outdoor Storage Area
- 1751 W Matthew DR - Sustana Fibers Flash Dryer System Addition
- 1405 Enterprise DR - New Contractor Warehouses
- 1840 S Broadway ST - New Valley Cabinet
- 2211 American BL - Nicolet Real Estate Addition
- 701 Millennium CT – Storage Shop USA Phase 2 & 3 Addition
Projects that are Recently Completed:
Projects that are Recently Denied:
- None
Additional Project Status Information
New Norfield Apartments |
|||||||
| Address: 1900 BLK Lebrun ST | |||||||
| Parcel Number: ED-1164-32-2 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Tyler Jorgensen, Slusarek Construction | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) |
Staff Review in Progress |
Plan Commission Review | Site Plan Approved or Denied | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Shop and Office |
|||||||
| Address: 700 BLK Millennium CT | |||||||
| Parcel Number: part of ED-2311 | |||||||
| City Funding: TIF 10 | |||||||
| Developer or Authorized Representative: Brandon Robaidek, Robert E Lee and Associates INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) |
Staff Review in Progress |
Plan Commission Review | Site Plan Approved or Denied | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
Altmayer Elementary School Re-pavement (includes new pavement) |
|||||||
| Address: 3001 Ryan RD | |||||||
| Parcel Number: ED-R28 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Jesse Becker, Point of Beginning INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jan 12, 2026 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | ||
|
Click here to see the site plan and developer contact information. |
|||||||
Mobius Parking Restripe and New Playground |
|||||||
| Address: 224 N Wisconsin ST | |||||||
| Parcel Number: ED-F0081-1 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Tanner Wojcik, Vierbicher | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jan 07, 2026 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
West De Pere High School Autos Addition |
|||||||
| Address: 665 Grant ST | |||||||
| Parcel Number: WD-864 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Nathan Stark, Bray Architects | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans |
Staff Review in Progress |
Plan Commission Review | Site Plan Approved or Denied | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||
New De Pere Parking Facility |
|||||||
| Address: 224 N Wisconsin ST | |||||||
| Parcel Number: ED-875 | |||||||
| City Funding: TIF 18 | |||||||
| Developer or Authorized Representative: Daniel Lindstrom, City of De Pere, Development Services | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Dec 23, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
MSC Expansion |
|||||||
| Address: 925 S Sixth ST | |||||||
| Parcel Number: WD-142, WD-144-1-1 | |||||||
| City Funding: City Project | |||||||
| Developer or Authorized Representative: Yeechue Thao, raSmith | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jan 27, 2026 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Soft Light Photography |
|||||||
| Address: 2000 BLK Profit PL | |||||||
| Parcel Number: ED-2384 | |||||||
| City Funding: TIF 17 | |||||||
| Developer or Authorized Representative: Shawn Jandry, McMahon Associates INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jan 07, 2026 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Phoenix of De Pere Multi-Unit Residential |
|||||||
| Address: 1100 BLK Employers BL | |||||||
| Parcel Number: WD-D0031-1 | |||||||
| City Funding: TIF 8 | |||||||
| Developer or Authorized Representative: Kyle Clark, Robert E Lee & Associates | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jan 23, 2023 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
American 3-Fab New Pavement and Screening |
|||||||
| Address: 2221 Innovation DR | |||||||
| Parcel Number: WD-L436-3 | |||||||
| City Funding: TIF 8 | |||||||
| Developer or Authorized Representative: Tonya Wagner, Vierbicher | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
|
Site Plan Approved - Oct 15, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Robinson West Laydown Yard |
|||||||
| Address: 2121 American BL | |||||||
| Parcel Number: WD-1040, WD-1042, WD-1043 | |||||||
| City Funding: Partially in TIF 11 | |||||||
| Developer or Authorized Representative: Steven Kolar, Payne & Dolan INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved- Oct 08, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Ninth Street Multi-Tenant Development |
|||||||
| Address: 114 S Ninth ST | |||||||
| Parcel Number: WD-D0200-4 | |||||||
| City Funding: TIF 13 | |||||||
| Developer or Authorized Representative: Drew Willmann, DeLeers Construction INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Sep 17, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
Belmark Plant 3 Expansion |
|||||||
| Address: 633 Heritage RD | |||||||
| Parcel Number: ED-F0094-1 | |||||||
| City Funding: TIF 10 | |||||||
| Developer or Authorized Representative: Carolyn Adler, McMahon Associates | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jul 21, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | ||
|
Click here to see the site plan and developer contact information. |
|||||||
New City Composting Yard Waste Site |
|||||||
| Address: 2005 Commerce DR | |||||||
| Parcel Number: ED-3100 | |||||||
| City Funding: City Project in TIF 10 | |||||||
| Developer or Authorized Representative: Eric Rakers, City Engineer, City of De Pere | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jul 25, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | ||
|
Click here to see the site plan and developer contact information. |
|||||||
New Robinson Metal Parking Lot |
|||||||
| Address: 2121 American BL | |||||||
| Parcel Number: WD-1040, WD-1041-1, WD-1041-2 | |||||||
| City Funding: Partially in TIF 11 | |||||||
| Developer or Authorized Representative: Steven Kolar, Payne & Dolan INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans |
Staff Review in Progress |
Plan Commission Review | Site Plan Approved or Denied | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||
New 550 West Mixed Use |
|||||||
| Address: 550 William ST | |||||||
| Parcel Number: ED-875-1 | |||||||
| City Funding: TIF 18 | |||||||
| Developer or Authorized Representative: Brandon Robaidek, Robert E Lee & Associates INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans |
Staff Review in Progress (C) |
Site Plan Approved - May 30, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Draco Pavement and Screening |
|||||||
| Address: 2385 Lawrence DR | |||||||
| Parcel Number: WD-L487 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Brandon Robaidek, Robert E Lee & Associates INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Jun 24, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Towneplace Suites Hotel |
|||||||
| Address: 215 N Wisconsin ST | |||||||
| Parcel Number: ED-861 | |||||||
| City Funding: TIF 18 | |||||||
| Developer or Authorized Representative: Brandon Robaidek, Robert E Lee & Associates INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - May 16, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Robinson Metal Warehouse Southeast Access Drive |
|||||||
| Address: 2121 American BL | |||||||
| Parcel Number: WD-1040, WD-1041-1, WD-1041-2 | |||||||
| City Funding: Partially in TIF 11 | |||||||
| Developer or Authorized Representative: Steven Kolar, Payne & Dolan INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans |
Staff Review in Progress |
Plan Commission Review | Site Plan Approved or Denied | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||
New Robinson Metal Transportation Terminal & Outdoor Storage |
|||||||
| Address: 450 Fortune AV | |||||||
| Parcel Number: WD-1040, WD-1041-1, WD-104102, WD-1043 | |||||||
| City Funding: TIF 11 | |||||||
| Developer or Authorized Representative: Steven Kolar, Payne & Dolan INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Mar 05, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
White Pillars Expansion |
|||||||
| Address: 403 N Broadway ST | |||||||
| Parcel Number: ED-752 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Bob Mach, Mach IV Engineering & Surveying LLC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Sep 30, 2025 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Amerilux Buildings |
|||||||
| Address: 2000 Commerce DR | |||||||
| Parcel Number: ED-3103 | |||||||
| City Funding: TIF 17 | |||||||
| Developer or Authorized Representative: Robert Mach, Mach IV Engineering & Surveying | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Dec 03, 2024 (C) | Permits Issued or Under Construction (C) | Certificate of Occupancy Issued (C) | Project Completed - Jan 12, 2026 (C) | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Contractor Warehouses |
|||||||
| Address: 1405 Enterprise DR | |||||||
| Parcel Number: ED-2077-1 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Mathew Litchfield, Mach IV Engineering & Surveying LLC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Site Plan Approved - Sep 03, 2024 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed | |
|
Click here to see the site plan and developer contact information. |
|||||||
New Valley Cabinet |
|||||||
| Address: 1840 S Broadway ST | |||||||
| Parcel Number: ED-F0101 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Mike Kohlbeck, McMahon Associates INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Plan Commission Review (C) | Site Plan Approved - Jun 11, 2024 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||
New Massman Corporate INC |
|||||||
| Address: 2005 Venture AV | |||||||
| Parcel Number: WD-D0076 | |||||||
| City Funding: TIF 11 | |||||||
| Developer or Authorized Representative: John Davel, Davel Engineering & Environmental INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans |
Staff Review in Progress (C) |
Plan Commission Review (C) | Site Plan Approved - Aug 22, 2025 (C) | Permits Issued or Under Construction (C) | Certificate of Occupancy Issued (C) | Project Completed Nov 18, 2025 (C) |
|
Click here to see the site plan and developer contact information. |
|||||||
Nicolet Real Estate Addition |
|||||||
| Address: 2211 American BL | |||||||
| Parcel Number: WD-1375 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Colin Meisel, Project Manager, Ruekert & Mielke INC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress |
Plan Commission Review (C) | Site Plan Approved - Dec 06, 2023 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||
Sustana Fibers Flash Dryer System Addition |
|||||||
| Address: 1751 W Matthew DR | |||||||
| Parcel Number: WD-364-D-526 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Dan Bassindale, Sustana Solutions | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans |
Staff Review in Progress (C) |
Plan Commission Review (C) | Site Plan Approved - Oct 10, 2024 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||
Storage Shop USA Phase 2 & 3 Addition |
|||||||
| Address: 701 Millennium CT | |||||||
| Parcel Number: ED-3090 | |||||||
| City Funding: No | |||||||
| Developer or Authorized Representative: Dave Anderson, Owner, Town and Country Development LLC | |||||||
| Project Status: (C) indicates Completed Step |
|||||||
| Submit Site Plan and Review Fee (C) | Developer Revising Plans (C) |
Staff Review in Progress (C) |
Plan Commission Review - Sep 26, 2022 (C) | Site Plan Approved - Oct 4, 2022 (C) | Permits Issued or Under Construction | Certificate of Occupancy Issued | Project Completed |
|
Click here to see the site plan and developer contact information. |
|||||||